Fabrication of the frame house structure (external wall structure, internal wall structure, ceiling, roof structure) |
|
|
|
|
Construction of the foundation (prefabricated point poles / foundation plate) |
|
|
|
|
Foundation waterproofing |
|
|
|
|
Sheathing of external walls with Steico SpecialDry wood fiber boards from 40mm |
|
|
|
|
Roof sheathing with Steico SpecialDry wood fiber boards from 40mm |
|
|
|
|
Roofing with Steico UDB membrane from the outside, counter patches C24 |
|
|
|
|
Covering the external walls with Steico UDB membrane (in the case of ventilated façade plus counter patches with C24, in the case of plaster there is no need) |
|
|
|
|
In the case of a wooden floor, there is a surcharge for insulation and protection of the floor against moisture in the amount of PLN 100.00 / m2 |
|
|
|
|
Roof sheathing with sheet metal for standing seam / roof tiles / tiles, including drainage, and finishing of the roof envelope (Soffit) |
|
|
|
|
Finishing of the plaster facade (in the case of a ventilated facade, there is a surcharge of PLN 120.00 / m2.) |
|
|
|
|
The facade covered with a seam sheet / Siberian larch cladding board. Surcharge in the amount of PLN 550.00 / m2 |
|
|
|
|
The facade covered with the Kebony facade board, which we distribute kebonypolska.pl |
|
|
|
|
Window and door joinery in the Energo+ 3-pane package - wooden or aluminum windows and doors |
|
|
|
|
Insulation of partitions of external and internal walls, ceiling / attic. Steico Flex 036 mats are used for insulation |
|
|
|
|
Preparation of installation partitions |
|
|
|
|
Execution of the chimney system with roof treatment |
|
|
|
|
Plumbing, connection to the building (without white installation) |
|
|
|
|
Electrical installations with switchboard, connection to the building (without white assembly) |
|
|
|
|
Additional insulation of the installation wall to break thermal bridges |
|
|
|
|
Vapor barrier |
|
|
|
|
Closing the walls inside the house (MFP + G-K board) |
|
|
|
|
Bringing internal walls under painting |
|
|
|
|
Preparation of wiring for photovoltaics |
|
|
|
|
Distribution of recuperation installations |
|
|
|
|
Ceilings brought to the state for painting / Stretch ceilings |
|
|
|
|
Installation for heating (electric underfloor, gas, heat pumps) |
|
|
|
|
House brought to a state for finishing |
|
|
|
|
Finishing the floor throughout the house |
|
|
|
|
Finishing of the bathroom with white assembly |
|
|
|
|
Finishing of water systems |
|
|
|
|
GROHE SENSE GUARD - INTELLIGENT CONTROL MODULE FOR WATER |
|
|
|
|
Finishing of the heating system |
|
|
|
|
Finishing of the recuperation system |
|
|
|
|
White electrical installation |
|
|
|
|
Painting the whole house |
|
|
|
|
Execution of drainage installation plus leveling of the area around the building |
|
|
|
|
House brought to the state of furnishing and residence |
|
|
|
|
The price also includes the assembly of furniture / wardrobes / kitchen |
|
|
|
|
Wooden terraces additionally payable in the amount from PLN 350.00 / m2 |
|
|
|
|